Reflections: Planning Proposal
From DaVinci
Contents |
Refleciton on 12/15/05
- By whole team
What we did well?
- At each Scrum meeting we know effort spent, effort estimated, and value earned
- Initially, effort for unplanned tasks was not tracked. Now, planning is more accurate
- Wideband delphi is working, but works better for tasks that we understand
What are the problems?
- Spent more time than planned due to unplanned tasks
- Needed to adjust task breakdown mechanism
- Better to have time reporting complete prior to Scrum meetings
- Need to make more metrics visible, such as workload distribution
- We have not analyzed the relevancy of performed tasks at the end of sprints