Project Status

From DaVinci

Contents


History
Sprint 5


Sprint 6

Goals

  • Have the necessary foundations in place for starting the implementation of Introduction of Port Groups (FE4002).
  • Gather knowledge on ATL in a way that the learning curve for the implementation of the first transformation using ATL is decreased.


Dates

  • Start: April 18th
  • End: May 5th


Deliverables

  • Use Cases: The scenario for the wizard where port group names, port group types, and connection names can be tailored. Furthermore, scenarios for three different contexts in which Introduction of Port Groups can be applied.
  • AADL Models: One input and one transformed AADL model for each of these three scenarios (i.e. 6 AADL models) clearly stating how an input model will be transformed into an output model.
  • Notional Architecture: Diagrams describing in more detail how to achieve the quality attributes marked with high priority.
  • ATL: Solution to the problem posed by the refines keyword and several .ecore files. This task has a dependency on the input that Peter Feiler can get for using several .ecore files.
  • Eclipse plug-in: Simple eclipse plug-in that displays a dialog box.


Current Status - May 2, 2006

Use Case Scenarios
  1. [Completed] Wizard for introduce port groups
  2. [Completed] Port(s)/Port Group(s) referenced in modes
  3. [Completed] Port(s)/Port Group(s) connected to one or more subcomponents
  4. [In Progress] Connection(s) referenced in properties
AADL Models
  1. [Completed] Port(s)/Port Group(s) referenced in modes
  2. [Completed] Port(s)/Port Group(s) connected to one or more subcomponents
  3. [Completed] Connection(s) referenced in properties
Notional Architecture
  1. [In Progress] Diagrams and description of notional architecture at greater detail
ATL
  1. [In Progress] Understanding problem with refines keyword and working with several .ecore files
Eclipse Plug-in
  1. [In Progress] Plug-in that displays a dialog box


Links to Ongoing Work


Week 3 - May 2, 2006

Progress

Week 3 Status


Problems


Feedback from Customer


Week 2 - Apr 25, 2006

Progress

Week 2 Status


Problems


Feedback from Customer


Week 1 - Apr 18, 2006

Progress

Not yet started


Problems


Feedback from Customer