Big Picture
From DaVinci
Contents |
Working Hours
In spring 2006:
2 people(New York): 12 hours 3 people(Pittsburgh): 12 hours 5 x 12 = 60 hours/per week
We work 6 days a week and 12 hours a week Each sprint is 3 weeks: 60 * 3 = 180 hours (per sprint)
In summer 2006:
1 person(New York): 36 hours 3 people(Pittsburgh): 48 hours 1 x 36 + 3 x 48 = 180 hours/per week
We work 5 days a week People in New York should contribute 36/5 ~ 7 hours/per day People in Pittsburgh should contribute 48/5 ~ 10 hours/per day Each sprint is 11 days: (180/5) * 11 = 396 hours (per sprint)
Sprint 6
Date: 4/20 ~ 5/12
- Notional Architecture v1.0 (Done)
- Architecture Review for v1.0 (Done)
- QA Plan v1.0 (Done)
- Requirements for Introduction of Port Groups (May 12)
- Acceptance Tests for Introduction of Port Groups (May 12)
Sprint 7
Planning: 5/22
Date: 5/23 ~ 6/6
- Tool Infrastructure Setup (May 22)
- Notional Architecture v2.0 (May 22-23)
- QA Plan v2.0 (May 22-23)
- Detailed Design for Introduction of Port Groups (May 23-25)
- Build Environment (May 22-26)
- ATL experiments (May 22 - Jun 6) – Decision Point
- Implementation of Introduction of Port Groups (May 22 – Jun 6)
- Requirements for Reasoning Framework Transformation (May 22 – Jun 6)
- Acceptance Tests for Reasoning Framework Transformation (May 22 – Jun 6)
- System Testing for Introduction of Port Groups (Jun 5-6)
- Architecture review for v2.0
Sprint 8
Planning: 6/7
Date: 6/8 ~ 6/22
- Notional Architecture v3.0 including ATL (Jun 7)
- Detailed Design for Reasoning Framework Transformation using ATL (Jun 7-9)
- Implementation of Reasoning Framework Transformation (Jun 7-22)
- Requirements for Omnet Transformation (Jun 7-22)
- Acceptance Tests for Omnet Transformation (Jun 7-22)
- System Testing for Reasoning Framework Transformation (Jun 21-22)
- Architecture review for v3.0
Sprint 9
Planning: 6/23
Date: 6/26 ~ 7/10
- Detailed Design for Omnet Transformation using ATL (Jun 23-26)
- Implementation of Omnet Transformation (Jun 23 – Jul 10)
- Requirements for Refactoring with ATL (Jun 23 – Jul 10)
- Acceptance Tests for Refactoring with ATL (Jun 23 – Jul 10)
- Requirements for non ATL Refactoring (Jun 23 – Jul 10)
- Acceptance Tests for non ATL Refactoring with ATL (Jun 23 – Jul 10)
- MOSP (Jun 26-30)
- System Testing for Omnet Transformation (Jul 7-10)
Sprint 10
Planning: 7/11
Date: 7/12 ~ 7/26
- Detailed Design for ATL and non ATL Refactoring (Jul 11-13)
- Implementation of ATL and non ATL Refactoring (Jul 11–26)
- System Testing for ATL and non ATL Refactoring (Jul 11-26)
Sprint 11
Planning: 7/27
Date: 7/28 ~ 8/10
- Documentation for implementing ATL Transformations (Jul 27 – Aug 10)
- Documentation for implementing non ATL Transformations (Jul 27 – Aug 10)
- Guideline for deciding implementation approach (Jul 27 – Aug 10)
- Removal of remaining defects (Jul 27 – Aug 10)
- System Testing for entire application (Jul 27 – Aug 10)
- EOSP (Aug 7-11)
Each Sprint
- Reflection Meeting
- Planning Meeting
- Risk Reevaluation
- Regular Customer Meeting