Big Picture

From DaVinci

Contents

Working Hours

  In spring 2006: 
2 people(New York): 12 hours 3 people(Pittsburgh): 12 hours 5 x 12 = 60 hours/per week
We work 6 days a week and 12 hours a week Each sprint is 3 weeks: 60 * 3 = 180 hours (per sprint)
  In summer 2006: 
1 person(New York): 36 hours 3 people(Pittsburgh): 48 hours 1 x 36 + 3 x 48 = 180 hours/per week
We work 5 days a week People in New York should contribute 36/5 ~ 7 hours/per day People in Pittsburgh should contribute 48/5 ~ 10 hours/per day Each sprint is 11 days: (180/5) * 11 = 396 hours (per sprint)

Sprint 6

Date: 4/20 ~ 5/12

  • Notional Architecture v1.0 (Done)
  • Architecture Review for v1.0 (Done)
  • QA Plan v1.0 (Done)
  • Requirements for Introduction of Port Groups (May 12)
  • Acceptance Tests for Introduction of Port Groups (May 12)

Sprint 7

Planning: 5/22

Date: 5/23 ~ 6/6

  • Tool Infrastructure Setup (May 22)
  • Notional Architecture v2.0 (May 22-23)
  • QA Plan v2.0 (May 22-23)
  • Detailed Design for Introduction of Port Groups (May 23-25)
  • Build Environment (May 22-26)
  • ATL experiments (May 22 - Jun 6) – Decision Point
  • Implementation of Introduction of Port Groups (May 22 – Jun 6)
  • Requirements for Reasoning Framework Transformation (May 22 – Jun 6)
  • Acceptance Tests for Reasoning Framework Transformation (May 22 – Jun 6)
  • System Testing for Introduction of Port Groups (Jun 5-6)
  • Architecture review for v2.0

Sprint 8

Planning: 6/7

Date: 6/8 ~ 6/22

  • Notional Architecture v3.0 including ATL (Jun 7)
  • Detailed Design for Reasoning Framework Transformation using ATL (Jun 7-9)
  • Implementation of Reasoning Framework Transformation (Jun 7-22)
  • Requirements for Omnet Transformation (Jun 7-22)
  • Acceptance Tests for Omnet Transformation (Jun 7-22)
  • System Testing for Reasoning Framework Transformation (Jun 21-22)
  • Architecture review for v3.0

Sprint 9

Planning: 6/23

Date: 6/26 ~ 7/10

  • Detailed Design for Omnet Transformation using ATL (Jun 23-26)
  • Implementation of Omnet Transformation (Jun 23 – Jul 10)
  • Requirements for Refactoring with ATL (Jun 23 – Jul 10)
  • Acceptance Tests for Refactoring with ATL (Jun 23 – Jul 10)
  • Requirements for non ATL Refactoring (Jun 23 – Jul 10)
  • Acceptance Tests for non ATL Refactoring with ATL (Jun 23 – Jul 10)
  • MOSP (Jun 26-30)
  • System Testing for Omnet Transformation (Jul 7-10)

Sprint 10

Planning: 7/11

Date: 7/12 ~ 7/26

  • Detailed Design for ATL and non ATL Refactoring (Jul 11-13)
  • Implementation of ATL and non ATL Refactoring (Jul 11–26)
  • System Testing for ATL and non ATL Refactoring (Jul 11-26)

Sprint 11

Planning: 7/27

Date: 7/28 ~ 8/10

  • Documentation for implementing ATL Transformations (Jul 27 – Aug 10)
  • Documentation for implementing non ATL Transformations (Jul 27 – Aug 10)
  • Guideline for deciding implementation approach (Jul 27 – Aug 10)
  • Removal of remaining defects (Jul 27 – Aug 10)
  • System Testing for entire application (Jul 27 – Aug 10)
  • EOSP (Aug 7-11)

Each Sprint

  • Reflection Meeting
  • Planning Meeting
  • Risk Reevaluation
  • Regular Customer Meeting