Borg Project Schedule (version 3)

Microsoft Project Image
Project Start Date: Mon 6/3/02
Progress Shown Through: Wed 6/12/02
Project End Date: Wed 8/9/02

Task List

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
M2 Prototype Delivery
0 daysFri 6/21/02Fri 6/21/024 
2
Develop Java/Browser side of M2 prototype
124.8 hrs?Mon 6/3/02Wed 6/19/02 Andrew[60%],Chiharu
3
Develop Apex side of M2 prototype
76.8 hrs?Fri 6/7/02Wed 6/19/02 Mike,Darby
4
Integrate and complete M2 prototype
19.2 hrsThu 6/20/02Fri 6/21/023Andrew,Chiharu,Mike,Darby
5
M5 Document update
20 hrs?Mon 6/24/02Wed 6/26/021Andrew,Chiharu,Mike,Darby
6
M4 Prototype Delivery
0 daysFri 7/12/02Fri 7/12/0210 
7
Understand HLA services
20 hrs?Wed 6/26/02Mon 7/1/025Andrew,Chiharu,Darby
8
Acquire and setup AMBR software
28.8 hrs?Wed 6/26/02Tue 7/2/025Mike
9
Understand AMBR simulation
30 hrs?Wed 6/26/02Tue 7/2/025Andrew,Chiharu,Mike,Darby
10
Develop time synchronization software
62.4 hrs?Tue 7/2/02Fri 7/12/029Andrew,Chiharu,Mike,Darby
11
M5 Document update
20 hrs?Fri 7/12/02Tue 7/16/026Andrew,Chiharu,Mike,Darby
12
M4 Full Software
0 daysFri 8/16/02Fri 8/16/0214 
13
Develop data handling software
72 hrs?Tue 7/16/02Tue 7/30/0211Andrew,Chiharu,Mike,Darby
14
Rearchitect for general interfaces
72 hrs?Tue 7/30/02Fri 8/16/0213Andrew,Chiharu,Mike,Darby
15
M5 Document Update
30 hrs?Fri 8/16/02Thu 8/22/0212Andrew,Chiharu,Mike,Darby
16
M1 Defect Correction
67.2 hrsThu 6/6/02Thu 8/1/02 Andrew,Chiharu,Mike,Darby
17
M1 Extensibility Document (first release)
15 hrs?Fri 6/7/02Mon 6/10/02 Andrew
18
M1 Extensbility Document (iterations)
18 hrs?Fri 6/21/02Fri 6/28/02 Andrew
19
M1 User Document
15 hrs?Wed 6/19/02Thu 6/20/02 Mike
20
EOSP Preparation
24 hrs?Tue 8/6/02Thu 8/8/02 Andrew,Chiharu,Mike,Darby
21
EOSP
9.6 hrsFri 8/9/02Fri 8/9/02 Andrew,Chiharu,Mike,Darby