Project Start Date:
Mon 6/3/02
Progress Shown Through:
Wed 6/12/02
Project End Date:
Wed 8/9/02
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | M2 Prototype Delivery | 0 days | Fri 6/21/02 | Fri 6/21/02 | 4 | |
| 2 | Develop Java/Browser side of M2 prototype | 124.8 hrs? | Mon 6/3/02 | Wed 6/19/02 | Andrew[60%],Chiharu | |
| 3 | Develop Apex side of M2 prototype | 76.8 hrs? | Fri 6/7/02 | Wed 6/19/02 | Mike,Darby | |
| 4 | Integrate and complete M2 prototype | 19.2 hrs | Thu 6/20/02 | Fri 6/21/02 | 3 | Andrew,Chiharu,Mike,Darby |
| 5 | M5 Document update | 20 hrs? | Mon 6/24/02 | Wed 6/26/02 | 1 | Andrew,Chiharu,Mike,Darby |
| 6 | M4 Prototype Delivery | 0 days | Fri 7/12/02 | Fri 7/12/02 | 10 | |
| 7 | Understand HLA services | 20 hrs? | Wed 6/26/02 | Mon 7/1/02 | 5 | Andrew,Chiharu,Darby |
| 8 | Acquire and setup AMBR software | 28.8 hrs? | Wed 6/26/02 | Tue 7/2/02 | 5 | Mike |
| 9 | Understand AMBR simulation | 30 hrs? | Wed 6/26/02 | Tue 7/2/02 | 5 | Andrew,Chiharu,Mike,Darby |
| 10 | Develop time synchronization software | 62.4 hrs? | Tue 7/2/02 | Fri 7/12/02 | 9 | Andrew,Chiharu,Mike,Darby |
| 11 | M5 Document update | 20 hrs? | Fri 7/12/02 | Tue 7/16/02 | 6 | Andrew,Chiharu,Mike,Darby |
| 12 | M4 Full Software | 0 days | Fri 8/16/02 | Fri 8/16/02 | 14 | |
| 13 | Develop data handling software | 72 hrs? | Tue 7/16/02 | Tue 7/30/02 | 11 | Andrew,Chiharu,Mike,Darby |
| 14 | Rearchitect for general interfaces | 72 hrs? | Tue 7/30/02 | Fri 8/16/02 | 13 | Andrew,Chiharu,Mike,Darby |
| 15 | M5 Document Update | 30 hrs? | Fri 8/16/02 | Thu 8/22/02 | 12 | Andrew,Chiharu,Mike,Darby |
| 16 | M1 Defect Correction | 67.2 hrs | Thu 6/6/02 | Thu 8/1/02 | Andrew,Chiharu,Mike,Darby | |
| 17 | M1 Extensibility Document (first release) | 15 hrs? | Fri 6/7/02 | Mon 6/10/02 | Andrew | |
| 18 | M1 Extensbility Document (iterations) | 18 hrs? | Fri 6/21/02 | Fri 6/28/02 | Andrew | |
| 19 | M1 User Document | 15 hrs? | Wed 6/19/02 | Thu 6/20/02 | Mike | |
| 20 | EOSP Preparation | 24 hrs? | Tue 8/6/02 | Thu 8/8/02 | Andrew,Chiharu,Mike,Darby | |
| 21 | EOSP | 9.6 hrs | Fri 8/9/02 | Fri 8/9/02 | Andrew,Chiharu,Mike,Darby |