| Minerva Team | |||||||||||||||
| ID | Task_Name | Start Date | Finish Date | Resp. | RP | WC | HL | JZ | Planned Total Hours | Actual Total Hours | Start Date Expired | Finish Date Expired | Finished | Planned Earned Value | Actual Earned Value |
| SRS | |||||||||||||||
| 1 | SRS write up and incorporating feedback | 5/29/01 | 6/4/01 | JZ | X | 12:00:00 | X | X | X | 0.5 | 0.5 | ||||
| High Level Design documents | |||||||||||||||
| 2 | Database Schema Creation | 5/29/01 | 6/4/01 | HL | X | X | 24:00:00 | X | X | X | 1 | 1 | |||
| 3 | Screen Design | 5/29/01 | 6/4/01 | RP | X | X | 24:00:00 | X | X | X | 1 | 1 | |||
| 4 | Architecture Document | 5/29/01 | 6/4/01 | WC | X | 12:00:00 | X | X | X | 0.5 | 0.5 | ||||
| 5 | Set up development environment | 5/30/01 | 6/4/01 | HL | X | X | 24:00:00 | X | X | X | 1 | 1 | |||
| 6 | Design, coding standard document | 5/29/01 | 6/4/01 | WC | X | X | 12:00:00 | 21:00:00 | X | X | X | 0.5 | 0.5 | ||
| 7 | Screen standards document | 5/31/01 | 6/4/01 | RP | X | X | 24:00:00 | 5:00:00 | X | X | X | 1 | 1 | ||
| Cycle 1 development (Student Mgmt) | 6/5/01 | 6/18/01 | |||||||||||||
| 8 | Add, update, delete features (design & coding) | 6/6/01 | 6/14/01 | JZ | X | 49:00:00 | 22:00:00 | X | X | X | 2.041667 | 2.04167 | |||
| 9 | Add, update, delete features - testing | 6/15/01 | 6/18/01 | JZ | X | 18:00:00 | X | X | X | 0.75 | 0.75 | ||||
| 10 | query feature - design and coding | 6/6/01 | 6/14/01 | RP | X | 49:00:00 | 15:00:00 | X | X | X | 2.041667 | 2.04167 | |||
| 11 | query feature - testing | 6/15/01 | 6/18/01 | RP | X | 18:00:00 | X | X | X | 0.75 | 0.75 | ||||
| 12 | database creation and stored procedures | 6/6/01 | 6/18/01 | HL | X | 67:00:00 | 30:00:00 | X | X | X | 2.791667 | 2.79167 | |||
| 13 | login feature | 6/6/01 | 6/18/01 | WC | X | 34:00:00 | 2:00:00 | X | X | X | 1.416667 | 1.41667 | |||
| 14 | report features in VB - for Student mgmt | 6/6/01 | 6/18/01 | WC | X | 33:00:00 | 15:00:00 | X | X | X | 1.375 | 1.375 | |||
| 15 | First demo for client (student mgmt module) | 6/21/01 | 6/21/01 | WC | X | X | X | X | 4:00:00 | 2:00:00 | X | X | X | 0.166667 | 0.16667 |
| Cycle 2 development (Program, Class and Course) | 6/19/01 | 7/5/01 | |||||||||||||
| 16 | incorporate client feedback for student mgmt | 6/21/01 | 6/26/01 | RP | X | X | 22:00:00 | 22:20:00 | X | X | X | 0.916667 | 0.91667 | ||
| 17 | program mgmt | 6/19/01 | 6/27/01 | HL | X | X | 33:00:00 | 12:00:00 | X | X | X | 1.375 | 1.375 | ||
| 18 | class mgmt | 6/19/01 | 6/27/01 | JZ | X | 28:00:00 | 10:00:00 | X | X | X | 1.166667 | 1.16667 | |||
| 19 | course mgmt | 6/19/01 | 6/27/01 | JZ | X | 28:00:00 | 12:00:00 | X | X | X | 1.166667 | 1.16667 | |||
| 20 | billing (incl add/remove organization) | 6/19/01 | 6/27/01 | RP | X | 22:00:00 | 12:20:00 | X | X | X | 0.916667 | 0.91667 | |||
| 21 | Reports(billing) | 6/19/01 | 7/3/01 | WC | X | 30:00:00 | 1:00:00 | X | X | X | 1.25 | 1.25 | |||
| 22 | Investigate connector between web and admin appl | 6/21/01 | 7/3/01 | WC | X | 20:00:00 | 5:00:00 | X | X | X | 0.833333 | 0.83333 | |||
| 23 | Database changes and stored procedures | 6/19/01 | 6/29/01 | HL | X | 33:00:00 | 34:00:00 | X | X | X | 1.375 | 1.375 | |||
| 24 | Testing all modules | 6/28/01 | 7/5/01 | JZ | X | X | X | 30:00:00 | 17:00:00 | X | X | X | 1.25 | 1.25 | |
| 25 | create system test plan | 6/25/01 | 7/17/01 | WC | X | 0 | 0 | ||||||||
| 26 | Second demo for client (all modules) | 7/5/01 | 7/5/01 | WC | X | X | X | X | 4:00:00 | 9:00:00 | X | X | X | 0.166667 | 0.16667 |
| Cycle 3 development (Data Migration & Integration) | 7/5/01 | 7/20/01 | |||||||||||||
| 27 | Data Migration | 7/5/01 | 7/20/01 | HL | X | 100:00:00 | 40:00:00 | X | X | X | 4.166667 | 4.16667 | |||
| 28 | Incorporate user access | 7/5/01 | 7/18/01 | RP | X | 24:00:00 | 4:30:00 | X | X | X | 1 | 1 | |||
| 29 | System testing | 7/6/01 | 7/20/01 | WC | X | X | X | X | 160:00:00 | 56:00:00 | X | X | X | 6.666667 | 6.66667 |
| 30 | Implement email connection admin and web appln | 7/6/01 | 7/18/01 | WC | X | 30:00:00 | 4:00:00 | X | X | X | 1.25 | 1.25 | |||
| 31 | Implement connector appln and MS-Access | 7/6/01 | 7/18/01 | JZ | X | 30:00:00 | 12:00:00 | X | X | X | 1.25 | 1.25 | |||
| 32 | User change requests | 7/6/01 | 7/18/01 | JZ | X | X | X | 40:00:00 | 8:30:00 | X | X | X | 1.666667 | 1.66667 | |
| 33 | Create production environment | 7/18/01 | 7/20/01 | HL | X | 18:00:00 | X | X | X | 0.75 | 0.75 | ||||
| Deployment Cycle | 7/23/01 | 8/3/01 | |||||||||||||
| 34 | Deploy application | 7/23/01 | 7/23/01 | RP | X | X | 10:00:00 | X | X | X | 0.416667 | 0.41667 | |||
| 35 | Transition plan | 7/23/01 | 8/3/01 | WC | X | 48:00:00 | X | X | X | 2 | 2 | ||||
| 36 | User Manual | 7/23/01 | 8/3/01 | RP | X | 36:00:00 | X | X | X | 1.5 | 1.5 | ||||
| 37 | Programmer's guide | 7/23/01 | 8/3/01 | JZ | X | 36:00:00 | X | X | X | 1.5 | 1.5 | ||||
| 38 | Post Mortem meeting | 7/30/01 | 7/30/01 | RP | X | X | X | X | 32:00:00 | X | X | X | 1.333333 | 1.33333 | |
| 39 | Bug fixing | 7/23/01 | 8/3/01 | JZ | X | X | X | X | 54:00:00 | X | X | X | 2.25 | 2.25 | |
| 40 | Administrator's guide | 7/23/01 | 8/3/01 | HL | X | 12:00:00 | X | X | X | 0.5 | 0.5 | ||||
| 41 | Data Migration documentation (programmers guide) | 7/23/01 | 8/3/01 | HL | X | 12:00:00 | X | X | X | 0.5 | 0.5 | ||||
| 42 | CMM Assessment meetings | 7/25/01 | 8/3/01 | RP | X | X | X | X | 20:00:00 | X | X | X | 0.833333 | 0.83333 | |
| Post Mortem and EOSP | 8/6/01 | 8/10/01 | |||||||||||||
| 43 | User training for MS-Access tables | 8/6/01 | 8/8/01 | RP | X | 8:00:00 | X | X | X | 0.333333 | 0.33333 | ||||
| 44 | Post Mortem report | 8/6/01 | 8/10/01 | RP | X | 35:00:00 | X | X | X | 1.458333 | 1.45833 | ||||
| 45 | Bug fixing | 8/6/01 | 8/9/01 | JZ | X | X | X | 24:00:00 | X | X | X | 1 | 1 | ||
| 46 | Slide creation and review | 8/6/01 | 8/9/01 | HL | X | X | X | X | 35:00:00 | X | X | X | 1.458333 | 1.45833 | |
| 47 | EOSP Dry Run | 8/6/01 | 8/6/01 | HL | X | X | X | X | 8:00:00 | X | X | X | 0.333333 | 0.33333 | |
| 48 | End of Semester Presentation | 8/10/01 | 8/10/01 | HL | X | X | X | X | 32:00:00 | X | X | X | 1.333333 | 1.33333 | |
| TOTAL | 1458:00:00 | 371:40:00 | 60.8 | 60.75 | |||||||||||
| Percentage complete : | 100.0% | 100.0% | |||||||||||||
| Note 1: Each week, the team has 48*4=192 hours of effort available. | |||||||||||||||
| However, the plan will assume a 30% effort for action items, meetings etc. | |||||||||||||||
| Hence, the effort for each week will be planned for approx. 134 hrs | |||||||||||||||
| Note 2: Actual effort will be tracked from cycle1 onwards. | |||||||||||||||