|
|
Client Meetings |
|
Team Minutes 01 (05/25/2001) |
Client Minutes 01 (06/08/2001) |
|
Team Minutes 02 (06/07/2001) |
Client Minutes 02 (07/05/2001) |
|
Team Minutes 03 (06/07/2001) |
|
|
Team Minutes 04 (06/21/2001) |
|
|
Team Minutes 05 (06/26/2001) |
|
|
Team Minutes 06 (07/05/2001) |
|
|
Team Minutes 07 (07/12/2001) |
|
|
Team Minutes 08 (07/19/2001) |
|
|
Team Minutes 09 (07/26/2001) |
|
|
|
Risk Statement |
Impact |
Probability |
Time |
Mitigation Strategies |
Follow-Up |
|
1 |
It is not known whether the write/delete capability will be included; customer might be dissatisfied. |
4 |
2 |
3 |
· Start earlier than expected · Build certutil (certificate utility found on the Mozilla web site) and find source code involved in write/delete options · Start with delete which seems easier and will give us experience |
· Certutil was built. Even though the source code was not converted directly, it did give a lot of pointers to what had to be done. · Delete capability was completed July 27th, 2001. |
|
2 |
Berkeley DB API will be ported without complete functional understanding; might replicate bugs ?make debugging difficult. |
3 |
2 |
3 |
· Intense unit and integration testing · Testing with Netscape databases that will require handling of large amount of certificates and different record types and keys |
· BerkeleyDBManager has been tested with NetscapeKeyStore and has worked well. · Several bugs have been found and fixed. |
|
3 |
There is no historical data for productivity for this project; time estimates could be optimistic. |
2 |
2 |
3 |
· Project tracking · Earned value · Weekly task assignment re-evaluation and schedule monitoring |
· It has been very difficult to estimate due to the differences in the code that needs to be converted. |
|
4 |
Not enough people on the team to be comfortable with the development schedule; not enough time. |
2 |
2 |
2 |
· Assign team members to tasks where they have the most experience and feel most comfortable with. |
· The Summer semester is complicated due to distractions coming from visiting students, courses, and interview processes. |
|
5 |
There will be no assigned technical writer in the summer ?we have to fit into the schedule of the SEI technical writer; take longer than planned. |
2 |
2 |
1 |
· Delivery date moved to August 3, 2001 · Contacted John Foreman for review on July 17, 2001 |
· On August 3, 2001 the TN will be delivered for Claire Dixon, but the process until actual publication might take 4 to 6 weeks. · Grace will be responsible for the follow-up on the publication process. |
|
Designation |
Name |
|
Quality Assurance and Support Manager and Client Liaison |
Pisey Huy |
|
Team Lead and Planning Manager |
Grace Lewis |
|
Process and Development Manager |
Ming-hsun Liu |
|
Mentor |
Cliff Huff |
|
Mentor |
Lynn Carter |
|
Client |
Scott Hissam |
|
Client |
Dan Plakosh |