| Agenda |
Team
Meeting |
| Participants |
Pisey Huy (Time Keeper)
Ming-hsun Liu (Minute Taker)
Grace Lewis (Facilitator) |
| Topics |
-
Review Open Action Items
-
Close every item except 191 and 189
-
Status
-
Krypto team is on schedule in terms of earned value (67.27%).
-
The schedule so far is ok, but we may fall off the schedule next week because
we haven't got the write/delete capability done yet.
-
Web Page Review
-
Some small things needs to be changed
-
Link is needed to the download from of NDBS 2.0. Will have to contact
client for information on where the download information is stored and
a new CGI script is needed.
-
Change the introduction to switch to the description page after a certain
second.
-
EOSP Slides Review
-
Small things needs to be changed
-
Insert verbs and nouns to make it clearer
-
Add sub-bullets to the issues slides
-
Add more items to the deliverables slide
-
Changed the implementation issues to issues and solutions slides
-
Add pie chart for effort in each development phase (100% Java and write/delete
capability)
-
Add EV slide as backup
-
Other minor issues are write on the draft EOSP slides
-
Need to look into keytool as a demo option if DIRS does not work.
|
| Action Items |
-
Grace - Write list of issues for write/delete to put on programmer's guide
and Web page.
-
Grace - Update EOSP slides
-
Grace - Talk to Clare Dixon for TN number
-
Grace - Take screen shots of DIRS for demo for it expires
-
Cliff - Send tag to Pisey on mega tag that enable a page to switch to another
page after a certain time.
-
Pisey - Link NDBS 2.0 Web site from Krypto Web site
-
Pisey - Update NDBS 2.0 Web site
-
Pisey - Send email to client on download form for NDBS 2.0
|