| Topics |
-
Review Open Action Items
-
Action item 167 and 169 remain open
-
Action item 170, 177, 178, 179 are closed.
-
Status
-
Krypto team is on schedule in terms of earned value = (33.64%).
-
Risk Review
-
Reviewed the top 5 risks and made August 4, 2001 date change to August
3, 2001.
-
Plan Review
-
Client meeting schedule and NetscapeKeyStore inspection
-
Need to let client know of schedule change for next client meeting
-
NetscapeKeyStore code overview is June 27 at 5:45PM
-
NetscapeKeyStore code review is June 29 at 4:15PM
-
BerkeleyDB is completed and the team will start on write/delete capability
this week
-
NDBSKeyStore is the next phase to be completed.
-
Review action items
-
Action item is minimal.
-
This is a quick status meeting for the team.
|