| Topics |
-
Open Action Item Review
-
AI # 168, 171, 174, 175 and 176 are closed and the rest remains open.
-
AI 171, John Foreman can do both the TN review and the internal presentation
-
Status
-
Report the TN modifications (by Scott) to Cliff.
-
Berkeley DB code is completely unit tested, but the Rose model still needs
to be updated..
-
Review the status and the EV with Cliff
-
Risk Management
-
Grace reports the top 5 risks idetified at last semester and the mitigation
strategies to Cliff .
-
Each team member did the risk evaluation and came out with the top 5 risks
-
Top 5 Risks are no.1, 11, 14, 12, 10.
-
Grace will update the risk management plan
-
There was also an issue on risk item #12 because there will be something
like South Korean students' visiting happens to distract the team.
-
Review the Test Plan
-
Grace has some comments on the test plan and will give the comments to
Pisey.
-
The output of NDBS should be clarified.
-
Add two more tests on Table 6
-
Detailed test plan about write/delete capability still needs to be determined
|