| Topics |
-
Role Assignment
-
Cliff has been informed of the roles for the summer semester.
-
Grace - Team Lead and Planning
-
Ming - Development and Process
-
Pisey - Quality Assurance, Support, and Client Liaison
-
Overall Plan
-
The team showed Cliff the WBS and the high-level summer schedule.
-
Cliff approves of the plan and wants to ensure that we are able to do what
we set out to do.
-
Cliff spoke to the team about setting aside a time where everyone will
be available for questions. The team will meet every weekday at 2PM
in the cave or via ICQ.
-
Grace will put the WBS and the spreadsheet on the web site.
-
Coding Plan
-
The coding strategy consists of 3 phases:
-
Berkeley Database
-
Netscape Keystore
-
NDBS Keystore
-
The team has a rough estimate of the line of code to be converted.
-
Team members has been assigned the classes on Berkeley DB.
-
Schedule for Weekly Team Meetings and Mentor Meetings.
-
The team will meet every Thursday at the SEI from 1:45PM - 2:45PM.
-
Each team member will send email to Cliff on mentor meeting day and time
and Cliff will check his schedule for availability.
-
Grace will reserve the room at the SEI.
-
There will be no team meeting next week, but Pisey and Ming will meet on
status.
-
Schedule for Client Meeting
-
The team decide on every other Friday at noon and lunch will be provided
at the SEI.
-
Pisey has already sent an email to the client and she will follow up on
it.
-
Date for Planning Meeting
-
The Planning Meeting will be on June 7, 2001.
|