Resource Start WBS Name Work Estimate Actual % Work Duration Actual Finish Finish Predecessors Counts? PV EV
0 7-Apr 0 Gryphon Cycle 4 365.5 hrs 0 0 84% 36 days NA 12-May 0 No 0 0
0 7-Apr 1 Prototype 1 7 hrs 0 0 100% 7 days NA 13-Apr 0 No 0 0
0 7-Apr 1.1 User Manual 7 hrs 0 0 100% 7 days NA 13-Apr 0 No 0 0
0 7-Apr 1.1.1 Review of Features Meeting 1 hr 0 0 100% 1 day NA 7-Apr 0 No 0 0
0 7-Apr 11 Reflective Practices 17 hrs 0 0 100% 28 days NA 4-May 0 No 0 0
0 7-Apr 13 WBS Creation 19 hrs 0 0 60% 35 days NA 11-May 0 No 0 0
0 7-Apr 14 Data Model Tasks 21 hrs 0 0 42% 28 days NA 4-May 0 No 0 0
0 7-Apr 14.2 Creation of Data Model 4 hrs 0 0 69% 28 days NA 4-May 0 No 0 0
0 7-Apr 14.3 RRLOE Strategy 11 hrs 0 0 0% 1 day NA 7-Apr 0 No 0 0
0 7-Apr 14.3.2 RRLOE Meetings 6 hrs 0 0 0% 1 day NA 7-Apr 0 No 0 0
0 7-Apr 2 Prototype 2 20 hrs 0 0 80% 5 days NA 11-Apr 0 No 0 0
0 7-Apr 4 User Manual Framework 7 hrs 0 0 100% 29 days NA 5-May 0 No 0 0
0 7-Apr 7 Overhead Rollup 56 hrs 0 0 92% 35 days NA 11-May 0 No 0 0
0 7-Apr 8 Matrix Roles 11.5 hrs 0 0 35% 35 days NA 11-May 0 No 0 0
0 7-Apr 8.1 Librarian 3.5 hrs 0 0 86% 35 days NA 11-May 0 No 0 0
0 11-Apr 15 Other Meetings 14 hrs 0 0 100% 1 day NA 11-Apr 0 No 0 0
0 11-Apr 15.1 Strategy Meeting 14 hrs 0 0 100% 1 day NA 11-Apr 0 No 0 0
0 12-Apr 9 Customer Meetings 47 hrs 0 0 91% 31 days NA 12-May 0 No 0 0
0 12-Apr 9.1 Data Model Meetings 18 hrs 0 0 78% 31 days NA 12-May 0 No 0 0
0 12-Apr 9.1.1 DM Meeting 4/12 12 hrs 0 0 100% 1 day NA 12-Apr 0 No 0 0
0 14-Apr 3 Prototype 3 52 hrs 0 0 97% 16 days NA 29-Apr 0 No 0 0
0 14-Apr 3.9 P3 Help 3 hrs 0 0 100% 14 days NA 27-Apr 0 No 0 0
0 14-Apr 5 SOW 15 hrs 0 0 100% 16 days NA 29-Apr 0 No 0 0
0 14-Apr 6 SRS 34 hrs 0 0 53% 18 days NA 1-May 0 No 0 0
0 14-Apr 6.1 SRS Development 25 hrs 0 0 60% 14 days NA 27-Apr 0 No 0 0
0 14-Apr 6.1.2 SRS Prototype Section 3 hrs 0 0 100% 3 days NA 16-Apr 0 No 0 0
0 14-Apr 9.2 Prototype Meetings 29 hrs 0 0 100% 14 days NA 27-Apr 0 No 0 0
0 14-Apr 9.2.1 P2 Meeting 15 hrs 0 0 100% 1 day NA 14-Apr 0 No 0 0
0 17-Apr 6.2 SRS Review 6 hrs 0 0 33% 13 days NA 29-Apr 0 No 0 0
0 17-Apr 6.2.1 SRS Prototype Format Review 2 hrs 0 0 100% 1 day NA 17-Apr 55 No 0 0
0 18-Apr 6.3 SRS Revisions 3 hrs 0 0 33% 14 days NA 1-May 0 No 0 0
0 21-Apr 14.1 Data Model Analysis 6 hrs 0 0 100% 7 days NA 27-Apr 0 No 0 0
0 21-Apr 14.1.1 Data Model Analysis Meeting 1 6 hrs 0 0 100% 7 days NA 27-Apr 0 No 0 0
0 21-Apr 6.1.1 SRS Data Model Section 12 hrs 0 0 100% 7 days NA 27-Apr 0 No 0 0
0 23-Apr 3.11 Integration 10 hrs 0 0 100% 4 days NA 26-Apr 24,20,21,22,23 No 0 0
0 24-Apr 3.1 User Manual 8 hrs 0 0 81% 6 days NA 29-Apr 0 No 0 0
0 25-Apr 5.2 SOW Review 7 hrs 0 0 100% 4 days NA 28-Apr 42 No 0 0
0 27-Apr 3.1.2 Verify Technical Accuracy of Manual 1 1.5 hrs 0 0 100% 1 day NA 27-Apr 15 No 0 0
0 27-Apr 9.2.2 P3 Meeting 14 hrs 0 0 100% 1 day NA 27-Apr 0 No 0 0
0 28-Apr 6.2.2 SRS Informal Internal Review 4 hrs 0 0 0% 2 days NA 29-Apr 56,57,52,53 No 0 0
0 5-May 10 Postmortem 16 hrs 0 0 100% 8 days NA 12-May 0 No 0 0
0 5-May 12 EOSP 29 hrs 0 0 100% 5 days NA 9-May 0 No 0 0
0 5-May 12.1 Slides 15 hrs 0 0 100% 4 days NA 8-May 0 No 0 0
0 5-May 4.3 Turnover 4.5 hrs 0 0 100% 1 day NA 5-May 0 No 0 0
0 6-May 12.2 Practicing 14 hrs 0 0 100% 4 days NA 9-May 0 No 0 0
0 12-May 9.1.2 DM Meeting 5/12 6 hrs 0 0 33% 1 day NA 12-May 0 No 0 0
AJ 7-Apr 1.1.1.1 Meeting: Review Prototype 1 Features 0.5 hrs 0.5 0.75 100% 1 day 14-Apr 7-Apr 0 Yes 30 30
AJ 7-Apr 4.1 User Manual Template Creation 1.5 hrs 1.5 1.5 100% 2 days 14-Apr 8-Apr 0 Yes 90 90
AJ 7-Apr 7.8 Project "B" 5 hrs 5 10 100% 35 days NA 11-May 0 No 0 0
AJ 9-Apr 1.1.2 Write Prototype 1 Manual 6 hrs 6 5 100% 5 days 14-Apr 13-Apr 3,36 Yes 360 360
AJ 11-Apr 15.1.2 Strategy Meeting 2 hrs 2 3 100% 1 day 14-Apr 11-Apr 0 No 0 0
AJ 12-Apr 9.1.1.1 DM Meeting 4/12 3 hrs 3 3.5 100% 1 day 14-Apr 12-Apr 0 No 0 0
AJ 14-Apr 4.2 Update Manual Template for IEEE 1 hr 1 0.5 100% 1 day 28-Apr 14-Apr 36 Yes 60 60
AJ 14-Apr 6.1.2.1 SRS Prototype Section Format 3 hrs 3 4.5 100% 3 days 5-May 16-Apr 0 Yes 180 180
AJ 14-Apr 9.2.1.2 P2 Meeting 2 hrs 2 2 100% 1 day 21-Apr 14-Apr 0 No 0 0
AJ 17-Apr 6.2.1.1 SRS Prototype Format Review 1 hr 1 0.75 100% 1 day 12-May 17-Apr 0 Yes 60 60
AJ 18-Apr 6.3.1 SRS Prototype Format Revision 1 hr 1 0 100% 0.5 days 12-May 18-Apr 59 Yes 60 60
AJ 24-Apr 3.1.1 Update manuals to 0.3.x 5 hrs 5 6.5 100% 3 days 28-Apr 26-Apr 0 Yes 300 300
AJ 25-Apr 5.2.1 SOW Pre-Review 2 hrs 2 2 100% 3 days 28-Apr 27-Apr 0 Yes 120 120
AJ 27-Apr 3.1.2.1 Verify Technical Accuracy 0.5 hrs 0.5 0.75 100% 1 day 28-Apr 27-Apr 0 Yes 30 30
AJ 27-Apr 9.2.2.2 P3 Meeting 2 hrs 2 2 100% 1 day 28-Apr 27-Apr 0 No 0 0
AJ 28-Apr 3.1.3 Revise Prototype 2 Manual 1.5 hrs 1.5 0 0% 2 days NA 29-Apr 16 Yes 90 0
AJ 28-Apr 5.2.2 SOW Review 1 hr 1 2.25 100% 1 day 5-May 28-Apr 44 Yes 60 60
AJ 5-May 10.2 Cycle 4 Postmortem 2 hrs 2 2 100% 8 days 12-May 12-May 0 Yes 120 120
AJ 5-May 12.1.1 Slides Creation 5 hrs 5 3 100% 4 days 12-May 8-May 0 No 0 0
AJ 5-May 4.3.1 Turnover User Manual 2 hrs 2 0 100% 1 day NA 5-May 0 No 0 0
AJ 6-May 12.2.1 Practice EOSP Slides 2 hrs 2 2 100% 4 days 12-May 9-May 0 No 0 0
AZ 7-Apr 11.1 RP Review 4 hrs 4 3 100% 28 days 12-May 4-May 0 No 0 0
AZ 7-Apr 7.1 Overhead 8 hrs 8 4 50% 35 days NA 11-May 0 No 0 0
AZ 7-Apr 8.2 Support 2 hrs 2 1 50% 35 days NA 11-May 0 No 0 0
AZ 11-Apr 15.1.1 Strategy Meeting 2 hrs 2 3 100% 1 day 14-Apr 11-Apr 0 No 0 0
AZ 14-Apr 3.5 Database Connectivity 3 hrs 3 6 100% 5 days 21-Apr 18-Apr 0 Yes 180 180
AZ 14-Apr 3.6 GUI Components 6 hrs 6 16 100% 8 days 28-Apr 21-Apr 0 Yes 360 360
AZ 14-Apr 3.7 Instruction Button 4 hrs 4 4 100% 12 days 28-Apr 25-Apr 0 Yes 240 240
AZ 14-Apr 9.2.1.1 P2 Meeting 2 hrs 2 3 100% 1 day 21-Apr 14-Apr 0 No 0 0
AZ 17-Apr 6.2.1.2 SRS Prototype Format Review 1 hr 1 3 100% 1 day 5-May 17-Apr 0 Yes 60 60
AZ 23-Apr 3.11.1 Integration 2 hrs 2 2 100% 4 days 28-Apr 26-Apr 0 Yes 120 120
AZ 27-Apr 9.2.2.1 P3 Meeting 2 hrs 2 2 100% 1 day 28-Apr 27-Apr 0 No 0 0
AZ 5-May 10.1 Cycle 4 Postmortem 2 hrs 2 2 100% 8 days 5-May 12-May 0 Yes 120 120
AZ 6-May 12.2.4 Watch Practice of EOSP 2 hrs 2 3 100% 4 days 12-May 9-May 0 No 0 0
BL 7-Apr 1.1.1.2 Meeting: Review Prototype 1 Features 0.5 hrs 0.5 0.5 100% 1 day 14-Apr 7-Apr 0 Yes 30 30
BL 7-Apr 11.2 RP Review 2 hrs 2 2 100% 28 days 12-May 4-May 0 No 0 0
BL 7-Apr 7.2 Overhead 5 hrs 5 6.25 100% 35 days NA 11-May 0 No 0 0
BL 7-Apr 7.7 Weekly Agenda Overhead 2 hrs 2 2.5 100% 35 days NA 11-May 0 No 0 0
BL 10-Apr 2.3 P2 Integration 8 hrs 8 7 100% 2 days 14-Apr 11-Apr 8,9 Yes 480 480
BL 11-Apr 15.1.3 Strategy Meeting 2 hrs 2 2.67 100% 1 day 14-Apr 11-Apr 0 No 0 0
BL 12-Apr 9.1.1.2 DM Meeting 4/12 3 hrs 3 2.67 100% 1 day 14-Apr 12-Apr 0 No 0 0
BL 14-Apr 3.3 N-Level Tree Printing 5 hrs 5 6 100% 7 days 21-Apr 20-Apr 0 Yes 300 300
BL 14-Apr 3.8 Manipulate Tree Components 1 hr 1 6 100% 0.5 days 21-Apr 14-Apr 0 No 0 0
BL 14-Apr 3.9.1 P3 Help Overhead 1 hr 1 9.25 100% 14 days 28-Apr 27-Apr 0 No 0 0
BL 14-Apr 9.2.1.3 P2 Meeting 3 hrs 3 2.5 100% 1 day 21-Apr 14-Apr 0 Yes 180 180
BL 18-Apr 6.1.3 Prototype 1 & 2 Content 4 hrs 4 0 0% 2 days NA 20-Apr 66 Yes 240 0
BL 27-Apr 9.2.2.3 P3 Meeting 2 hrs 2 2 100% 1 day 28-Apr 27-Apr 0 No 0 0
BL 28-Apr 6.2.2.1 SRS Review/Prep 2 hrs 2 0.5 0% 2 days NA 29-Apr 0 Yes 120 0
BL 30-Apr 6.3.2 SRS Revision 2 hrs 2 1 0% 2 days NA 1-May 62 Yes 120 0
BL 5-May 10.3 Cycle 4 Postmortem 4 hrs 4 2.65 100% 8 days 12-May 12-May 0 Yes 240 240
BL 6-May 12.2.5 Watch Practice of EOSP 2 hrs 2 3.5 100% 4 days 12-May 9-May 0 No 0 0
BL 12-May 9.1.2.1 DM Meeting 5/12 2 hrs 2 0 0% 1 day NA 12-May 0 No 0 0
GT 7-Apr 11.3 RP Review 4 hrs 4 2 100% 28 days 12-May 4-May 0 No 0 0
GT 7-Apr 7.3 Overhead 6 hrs 6 7.17 100% 35 days NA 11-May 0 No 0 0
GT 7-Apr 8.1.2 Backup Librarian 1 hr 1 0.5 50% 35 days NA 11-May 0 No 0 0
GT 8-Apr 2.1 P2 Tab Sheet Investigation 3 hrs 3 2 100% 2 days 14-Apr 9-Apr 0 Yes 180 180
GT 11-Apr 15.1.4 Strategy Meeting 2 hrs 2 2.67 100% 1 day 14-Apr 11-Apr 0 Yes 0 0
GT 14-Apr 3.2 N-Level Tree Parsing and Saving 5 hrs 5 14 100% 7 days 28-Apr 20-Apr 0 Yes 300 300
GT 14-Apr 5.1 SOW Update 6 hrs 6 5 100% 11 days 28-Apr 24-Apr 0 Yes 360 360
GT 14-Apr 9.2.1.4 P2 Meeting 2 hrs 2 2.5 100% 1 day 21-Apr 14-Apr 0 No 0 0
GT 27-Apr 9.2.2.4 P3 Meeting 2 hrs 2 1.67 100% 1 day 28-Apr 27-Apr 0 No 0 0
GT 28-Apr 5.2.3 SOW Review 2 hrs 2 3 100% 1 day 5-May 28-Apr 44 No 0 0
GT 28-Apr 6.2.2.2 SRS Review/Prep 2 hrs 2 0 0% 2 days NA 29-Apr 0 Yes 120 0
GT 29-Apr 5.3 SOW Revision 2 hrs 2 1 100% 1 day 12-May 29-Apr 43 Yes 120 120
GT 5-May 10.4 Cycle 4 Postmortem 2 hrs 2 2 100% 8 days 12-May 12-May 0 Yes 120 120
GT 6-May 12.2.6 Watch Practice of EOSP 2 hrs 2 1 100% 4 days 12-May 9-May 0 No 0 0
SK 7-Apr 11.4 RP Review 2 hrs 2 1.2 100% 28 days 12-May 4-May 0 No 0 0
SK 7-Apr 2.4 P2 Data Module (Saving) 4 hrs 4 3.67 0% 2 days NA 8-Apr 0 Yes 240 0
SK 7-Apr 2.5 Database population 2 hrs 2 3.5 100% 1 day 14-Apr 7-Apr 0 Yes 120 120
SK 7-Apr 7.4 Overhead 8 hrs 8 16.25 100% 35 days NA 11-May 0 No 0 0
SK 7-Apr 7.9 Customer Liason 3 hrs 3 3.91 100% 35 days NA 11-May 0 No 0 0
SK 7-Apr 8.1.1 Librarian 2.5 hrs 2.5 4.55 100% 35 days NA 11-May 0 No 0 0
SK 11-Apr 15.1.5 Strategy Meeting 2 hrs 2 2.67 100% 1 day 14-Apr 11-Apr 0 No 0 0
SK 14-Apr 3.10 P3 Overhead 2 hrs 2 12 100% 14 days 28-Apr 27-Apr 0 No 0 0
SK 14-Apr 3.4 N-Level Tree Saver 5 hrs 5 2.75 100% 9 days 21-Apr 22-Apr 0 Yes 300 300
SK 14-Apr 9.2.1.5 P2 Meeting 2 hrs 2 2.5 100% 1 day 21-Apr 14-Apr 0 No 0 0
SK 18-Apr 6.1.4 Prototype 3 Content 6 hrs 6 0 0% 3 days NA 21-Apr 66 Yes 360 0
SK 23-Apr 3.11.2 Integration 8 hrs 8 11.2 100% 4 days 28-Apr 26-Apr 0 Yes 480 480
SK 27-Apr 3.1.2.2 Verify Technical Accuracy 1 hr 1 0.5 100% 0.5 days 28-Apr 27-Apr 0 Yes 60 60
SK 27-Apr 9.2.2.5 P3 Meeting 2 hrs 2 2.25 100% 1 day 28-Apr 27-Apr 0 Yes 120 120
SK 28-Apr 5.2.4 SOW Review 2 hrs 2 3.1 100% 1 day 5-May 28-Apr 44 No 0 0
SK 5-May 10.5 Cycle 4 Postmortem 2 hrs 2 2.33 100% 8 days 5-May 12-May 0 Yes 120 120
SK 5-May 4.3.2 Turnover User Manual 2.5 hrs 2.5 1.75 100% 1 day NA 5-May 0 No 0 0
SK 6-May 12.2.7 Watch Practice of EOSP 2 hrs 2 3 100% 4 days 12-May 9-May 0 No 0 0
SS 7-Apr 11.5 RP Review 3 hrs 3 1.33 100% 28 days 12-May 4-May 0 No 0 0
SS 7-Apr 13.3 Planning and Scheduling 8 hrs 8 0.5 6% 35 days NA 11-May 0 No 0 0
SS 7-Apr 14.3.1 RRLOE Strategy Development 3 hrs 3 0 0% 1 day NA 7-Apr 0 No 0 0
SS 7-Apr 14.3.2.1 RRLOE Meeting 3 hrs 3 0 0% 1 day NA 7-Apr 0 No 0 0
SS 7-Apr 14.3.3 RRLOE Strategy Documentation 2 hrs 2 0 0% 1 day NA 7-Apr 0 No 0 0
SS 7-Apr 7.10 Planning Overhead 3 hrs 3 7.08 100% 35 days NA 11-May 0 No 0 0
SS 7-Apr 7.5 Overhead 4 hrs 4 7.17 100% 35 days NA 11-May 0 No 0 0
SS 8-Apr 2.2 P2 Data Retrieval Method 3 hrs 3 3 100% 2 days 14-Apr 9-Apr 0 Yes 180 180
SS 11-Apr 13.1 WBS v4.01 5 hrs 5 4 100% 3 days 14-Apr 13-Apr 0 Yes 0 0
SS 11-Apr 15.1.6 Strategy Meeting 2 hrs 2 2.67 100% 1 day 14-Apr 11-Apr 0 No 0 0
SS 12-Apr 9.1.1.3 DM Meeting 4/12 3 hrs 3 3 100% 1 day 14-Apr 12-Apr 0 Yes 180 180
SS 14-Apr 13.2 WBS v.4.1 6 hrs 6 2.5 100% 7 days 21-Apr 20-Apr 143 Yes 0 0
SS 14-Apr 9.2.1.6 P2 Meeting 2 hrs 3 2.5 100% 1 day 21-Apr 14-Apr 0 No 0 0
SS 21-Apr 14.1.1.1 Data Model Analysis Meeting 1 3 hrs 3 4 100% 7 days 28-Apr 27-Apr 0 Yes 0 0
SS 21-Apr 3.9.2 P3 Help Overhead 1 hr 1 1 100% 7 days 28-Apr 27-Apr 0 No 0 0
SS 21-Apr 6.1.1.2 SRS Data Model Section 4 hrs 4 3 100% 7 days 5-May 27-Apr 0 Yes 240 240
SS 27-Apr 9.2.2.6 P3 Meeting 2 hrs 2 2 100% 1 day 28-Apr 27-Apr 0 No 0 0
SS 5-May 10.6 Cycle 4 Postmortem 2 hrs 2 0.75 100% 8 days 5-May 12-May 0 Yes 120 120
SS 5-May 12.1.2 Slides Creation 5 hrs 5 4 100% 4 days 12-May 8-May 0 No 0 0
SS 6-May 12.2.2 Practice EOSP Slides 2 hrs 2 1.5 100% 4 days 12-May 9-May 0 No 0 0
SS 12-May 9.1.2.2 DM Meeting 5/12 2 hrs 2 4 100% 1 day 12-May 12-May 0 Yes 120 120
ZS 7-Apr 11.6 RP Review 2 hrs 2 2.5 100% 28 days 12-May 4-May 0 No 0 0
ZS 7-Apr 14.2.1 Old Data Model 2 hrs 4 1.5 38% 28 days NA 4-May 0 No 0 0
ZS 7-Apr 14.3.2.2 RRLOE Meeting 3 hrs 3 0 0% 1 day NA 7-Apr 0 No 0 0
ZS 7-Apr 7.11 Web Page Maintenance 4 hrs 4 3.25 81% 35 days NA 11-May 0 No 0 0
ZS 7-Apr 7.6 Overhead 8 hrs 8 8.5 100% 35 days NA 11-May 0 No 0 0
ZS 7-Apr 8.3 QA 6 hrs 6 0 0% 35 days NA 11-May 0 No 0 0
ZS 11-Apr 15.1.7 Strategy Meeting 2 hrs 2 3 100% 1 day 14-Apr 11-Apr 0 No 0 0
ZS 12-Apr 9.1.1.4 DM Meeting 4/12 3 hrs 3 3 100% 1 day 14-Apr 12-Apr 0 Yes 180 180
ZS 14-Apr 9.2.1.7 P2 Meeting 2 hrs 3 2.5 100% 1 day 21-Apr 14-Apr 0 No 0 0
ZS 21-Apr 14.1.1.2 Data Model Analysis Meeting 1 3 hrs 3 4 100% 7 days 28-Apr 27-Apr 0 Yes 0 0
ZS 21-Apr 3.9.3 P3 Help Overhead 1 hr 1 6.5 100% 7 days 28-Apr 27-Apr 0 No 0 0
ZS 21-Apr 6.1.1.1 SRS Data Model Section 8 hrs 8 6 100% 7 days 5-May 27-Apr 0 Yes 480 480
ZS 27-Apr 9.2.2.7 P3 Meeting 2 hrs 2 2 100% 1 day 28-Apr 27-Apr 0 No 0 0
ZS 28-Apr 14.2.2 Data Model v0.1 2 hrs 2 5.16 100% 2 days 5-May 29-Apr 148 Yes 0 0
ZS 5-May 10.7 Cycle 4 Postmortem 2 hrs 2 1.5 100% 8 days 12-May 12-May 0 Yes 120 120
ZS 5-May 12.1.3 Slides Creation 5 hrs 5 7 100% 4 days 12-May 8-May 0 No 0 0
ZS 6-May 12.2.3 Practice EOSP Slides 2 hrs 2 5 100% 4 days 12-May 9-May 0 No 0 0
ZS 12-May 9.1.2.3 DM Meeting 5/12 2 hrs 2 0 0% 1 day NA 12-May 0 No 0 0
                             
        0 369.5 398 0%     0-Jan 0   8970 7680