| 36668 | 36675 | 36682 | 36689 | 36696 | 36703 | 36710 | |
| 7/3/00 | 7/10/00 | 7/17/00 | 7/24/00 | 7/31/00 | 8/7/00 | 8/14/00 | |
| Planned Value | 0 | 8220 | 1620 | 0 | 900 | 0 | 0 |
| Cumulative PV | 0 | 8220 | 9840 | 9840 | 10740 | 10740 | |
| EV | 0 | 0 | 0 | 0 | 0 | 0 | |
| Cumulative EV | 0 | 0 | 0 | 0 | 0 | 0 | |
| Weekly | 0.00% | 0.00% | #DIV/0! | 0.00% | |||
| Cumulative | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | ||
| Effort by Week | 30 | 396 | 108 | 4 | 69 | 0 | 607 |
| Earned hrs by Week | 137 | 27 | 0 | 15 | |||
| Earned Value By Week By Resource Matrix | |||||||
| AZ | 2160 | 0 | 0 | 900 | 0 | ||
| BL | 1500 | 1020 | 0 | 0 | 0 | ||
| GT | 1500 | 360 | 0 | 0 | 0 | ||
| SK | 0 | 240 | 0 | 0 | 0 | ||
| SS | 1800 | 0 | 0 | 0 | 0 | ||
| ZS | 1260 | 0 | 0 | 0 | 0 | ||
| 8220 | 1620 | 0 | 900 | 0 | 10740 | ||
| Total Effort By Week By Resource Matrix | |||||||
| AZ | 82 | 17 | 0 | 15 | 0 | ||
| BL | 85 | 32 | 0 | 8 | 0 | ||
| GT | 59 | 21 | 3 | 15 | 0 | ||
| SK | 22 | 16 | 1 | 15 | 0 | ||
| SS | 76 | 16 | 0 | 8 | 0 | ||
| ZS | 72 | 6 | 0 | 8 | 0 | ||
| 396 | 108 | 4 | 69 | 0 | 577 | ||
| Adjusted Effort By Week By Resource Matrix | |||||||
| AZ | 33 | 15 | 0 | 15 | 0 | ||
| BL | 19 | 30 | 0 | 8 | 0 | ||
| GT | 19 | 19 | 3 | 15 | 0 | ||
| SK | 1 | 12 | 1 | 15 | 0 | ||
| SS | 32 | 14 | 0 | 8 | 0 | ||
| ZS | 17 | 4 | 0 | 8 | 0 | ||
| 121 | 94 | 4 | 69 | 0 | 288 | ||