Current Plan

From ZenWiki

Jump to: navigation, search

Contents

Current Plan

Plan for Fall 2007

Summer 2007 Plan

The following graph represents a simplified version of the plan Team Zen is currently planning to working to, from a component-based perspective.

Description:

  • The component names on the left represent all major components that must be built in the system.
  • The different colors on the graph simply represent the order of the tasks and the weeks which they will be performed.
  • The thick vertical lines on the graph represent major milestones. The thin vertical lines represent minor milestones.

Updated Plan, 7-25-07

  • The plan was slightly modified here to show that the engagement setup piece was being reassigned and moved up in the schedule.

Image:Summer_Plan-Updated_7_25_07.GIF


Plan History

Updated Plan, 7-18-07

  • The plan was slightly modified here to reflect that Server UI testing is an ongoing process instead of a discrete event.

Image:Summer_Plan-Updated_7_18_07.GIF


Updated Plan, 6-27-07

  • The only thing changed here was a rescheduling of the first delivery (based on customer needs).

Image:Summer_Plan-Updated_6_27_07.GIF

Updated Plan, 6-14-07

  • The only thing changed here was a rescheduling of the first delivery (based on customer needs).

Image:Summer_Plan-Updated_6_14_07.GIF

First Update

  • The only thing changed here was a swapping in the order of modules for Allen.

Image:Summer_Plan-Updated_6_12_07.GIF


Initial Plan

Image:Summer Plan-Initial.GIF

Personal tools