The following graph represents a simplified version of the plan Team Zen is currently planning to working to, from a component-based perspective.
Description:
- The component names on the left represent all major components that must be built in the system.
- The different colors on the graph simply represent the order of the tasks and the weeks which they will be performed.
- The thick vertical lines on the graph represent major milestones. The thin vertical lines represent minor milestones.
Updated Plan, 7-25-07
- The plan was slightly modified here to show that the engagement setup piece was being reassigned and moved up in the schedule.
Plan History
Updated Plan, 7-18-07
- The plan was slightly modified here to reflect that Server UI testing is an ongoing process instead of a discrete event.
Updated Plan, 6-27-07
- The only thing changed here was a rescheduling of the first delivery (based on customer needs).
Updated Plan, 6-14-07
- The only thing changed here was a rescheduling of the first delivery (based on customer needs).