Team progress reviews

04/07/06

Team Simulacrum

Date

Progress

Comments/Risks

2006/04/07

Proposal:QA Plan and Risk Management Plan to be reviewed by team
SOW: accepted
SRS: not baselined
Architectural documents: Architectural drivers. Notional Architecture.
Process definition: Operations proposal
SPMP: N/A

Reflection: Reflection meeting held on 03/06. Next on 04/08.

Case study paper:N/A

Performing 10 experiments to refine architecture. Planning for a review with the customers presence for mid-April. Reassessed the plan, and pushed back 6p for summer

 

 

 

Team DaVinci

Date

Progress

Comments/Risks

2005/04/07

 

High level notional architecture done

Software process specification revised

Requirement Elicitation: use case, testing criteria

Regular Customer meeting

 

We have many problems among the team, such as:

low moral

low productivity

missing common working hour...

 

Find the root causes?

 

 

 

03/24/06

Team Simulacrum

Date

Progress

Comments/Risks

2006/03/24

Proposal:Design Proposal reviewed; QA Plan and Risk Management Plan in review by mentors
SOW: accepted
SRS: not baselined
Architectural documents: Architectural drivers. Notional Architecture.
Process definition: Operations proposal
SPMP: N/A

Reflection: Reflection meeting held on 03/06. Next on 04/08

Case study paper:N/A

Went through stages 4 and 5 of ACDM. Moving to 6e and 7e when more experiments will be performed. Planning for customer to fly in for architectural review in mid April

 

 

 

Team Serendipity

Date

Progress

Comments/Risks

2006/3/24

Proposal: Will updated this week after the reflection meeting of the second cycle
SOW:
the updated version hasn’t been signed yet.
SRS: Will start the draft this week. Requirements are being refined with the client
Architectural documents: Notional architecture is in fifth iteration. Will start evaluation next week
Process definition: N/A
SPMP: N/A

Reflection: carried out a second reflection meeting this week.

Case study paper: N/A

-         Identified risks and ranked them. Mitigation and tracking will be carried out next week

-         Working on the long term plan and how to improve status tracking

-         Communication problems are leading to frustration within the team.

 

 

 

Team DaVinci

Date

Progress

Comments/Risks

2006/03/24

Proposal:Implemenation Proposal done

SOW: done

SRS: done

Architecture documentation: stated

Process definition: done

SPMP: N/A
Reflection: sprint 4 reflection done

Case study paper: N/A

finished our MOSP

MOSP reflection

Working on refining our planning meeting

 

 

 

02/02/2006

Team Simulacrum

Date

Progress

Comments/Risks

2006/02/02

Proposal: Started working on design proposal
SOW:Done.
SRS: Done.
Architectural documents: Not started
Process definition: Done.
SPMP: Not defined

Reflection: Next scheduled for monday

Case study paper:N/A

We decided to use the Academic License.
We are not experienced witht the requirements refinement process.

 

 

 

 

Team DaVinci

Date

Progress

Comments/Risks

2006/02/02

Proposal:

Development Proposal progressing

SRE:

SRE session finished


Productivity is not very well

Requirement elicitation hasn't been done much yet

 

 

 

 

02/17/2006

Team Simulacrum

Date

Progress

Comments/Risks

2006/02/17

Proposal: In progress Design
SOW: accepted

SRS: not baselined
Architectural documents: Architectural drivers
Process definition: Operations proposal
SPMP: N/A

Reflection: Reflection meeting held on 02/10

Case study paper:N/A

Acquired Academic License for Opnet; Opnet learning curve is steep;Working on experiments;